Maintenance in SG-Singapore-M-1 region

Scheduled Maintenance Report for Skytap

Completed

The scheduled maintenance has been completed.
Posted Mar 15, 2025 - 22:26 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 15, 2025 - 16:00 UTC

Scheduled

Skytap will be performing maintenance in the SG-Singapore-M-1 region on:
March 16 2025, 12:00 AM Singapore time (March 15 2025 16:00 UTC)

The maintenance duration is expected to be up to 7 hours.

During this maintenance window:

12:00 AM Singapore time: All LPARs and VMs in the region will be locked. A subset of VMs/LPARs in the region will be shutdown. If your account is affected by this shutdown, you will have received a separate notification. Effects of locking include:
• VMs and LPARs are unable to change state (ie, cannot be suspended, resumed, shutdown, or powered off)
• Environments are unable to be copied

1:50 AM Singapore time: LPARs and VMs that were shutdown begin to power on; this process may take up to 1.75 hours to complete.

4:30 AM to 6:00 AM AM Singapore time: During this period LPARs and VMs in the region may experience short disruptions to various networking services in the region.

6:10 AM Singapore time: All LPARs and VMs in the region will be unlocked. This process may take up to 15 minutes to complete.


Skytap will actively monitor system health and operations during this time and will post any related service impact to the Skytap Health Dashboard at https://status.skytap.com/

If you have any questions about this maintenance, you can open a support request by sending an email to support@skytap.com
Posted Feb 13, 2025 - 23:19 UTC
This scheduled maintenance affected: SG-Singapore-M-1 (SG-Singapore-M-1 POWER Compute, SG-Singapore-M-1 x86 Compute, SG-Singapore-M-1 Network).